EDF delays start of UK Hinkley Point nuclear plant

French energy company EDF said the launch of its Hinkley Point C nuclear plant project in Britain would be delayed until June 2026 as it also lifted cost forecasts.

“The project completion costs are now estimated in the range of ยฃ22bn – ยฃ23bn,” the company said in a statement on Wednesday, against a 2019 estimate of ยฃ21.5bn – ยฃ22.5bn.

“The start of electricity generation from (Hinkley’s) Unit 1 is now expected in June 2026, compared to end-2025 as initially announced in 2016,” it added.

Once completed, Hinkley will generate electricity for around six million, or 7%, of the UK’s homes.

EDF said the delay and increased costs mean the expected rate of return from its investment would fall to between 7.1% – 7.2% from 7.6% – 7.8% .

It added that a delay of nine to 15 months for Units 1 and 2 of the project would cost around ยฃ700m and hit the rate of return by a further 0.3%.

Related Articles

Sign up to the Wealth DFM Newsletter

Name

Trending Articles

Wealth DFM Talk is our flagship podcast, that fits perfectly into your busy life, bringing the latest insight, analysis, news and interviews to you, wherever you are.

Wealth DFM Talk Podcast – listen to the latest episode